Mining Stock News - Ivanhoe Mines (TSX: IVN) (OTCQX: IVPAF) Issues 2023 First Quarter Financial Results, and Overview of Construction and Exploration Activities
- Kamoa-Kakula sold 86,777 tonnes of payable copper during the quarter and recognized record revenue of $689 million, as well as record EBITDA of $452 million
- Ivanhoe Mines recorded Q1 2023 profit of $82 million, net of $31 million non-cash loss on the convertible bond fair valuation
- Kamoa-Kakula produced 93,603 tonnes of copper in Q1 2023, including a record 34,915 tonnes of copper in March, following debottlenecking program completed ahead of schedule
- Kamoa-Kakula's quarterly cost of sales total $1.25 per lb. of payable copper; C1 cash costs of $1.42 per lb. towards the lower end of guidance
- Kamoa-Kakula's Phase 3 expansion on track for Q4 2024; boosting copper production to a ten-year average of 620,000 tonnes per annum, at C1 cash cost of $1.22/lb.
- Ivanhoe Mines commences optimization work on installing hoisting capacity in Shaft 3 at the Tier-One Platreef palladium, nickel, platinum, rhodium, copper and gold mine in South Africa
- Ivanhoe Mines agrees off-take terms with Gécamines and Glencore for 100% of Kipushi's zinc concentrate, together with US$250 million facility
Johannesburg, South Africa - May 3, 2023 (Newsfile Corp.) (Investorideas.com Newswire) Ivanhoe Mines' (TSX: IVN) (OTCQX: IVPAF) President Marna Cloete and Chief Financial Officer David van Heerden are pleased to present the company's financial results for the three months ended March 31, 2023. Ivanhoe Mines is a leading Canadian mining company that is advancing its four principal mining and exploration projects in Southern Africa: the Phase 3 expansion of the Kamoa-Kakula Copper Complex in the Democratic Republic of Congo (DRC) that commenced commercial operations in July 2021; the construction of the Platreef palladium, nickel, platinum, rhodium, copper and gold project in South Africa, scheduled for first production in the third quarter of 2024; the restart of the historic Kipushi zinc-copper-lead-germanium mine in the DRC, also scheduled for first production in the third quarter of 2024; and the exploration for new copper discoveries on Ivanhoe's 2,407-square-kilometre Western Foreland exploration project, which is adjacent to Kamoa-Kakula. All figures are in U.S. dollars unless otherwise stated.
FINANCIAL HIGHLIGHTS
- Ivanhoe Mines recorded a profit of $82 million for Q1 2023, compared to a profit of $22 million for the same period in 2022. The profit in the quarter is net of a $31 million non-cash loss on the fair value adjustment of the embedded derivative financial liability of the convertible bond, resulting predominantly from a 14% increase in the share price from C$10.70 per share to C$12.21 per share at quarter end. The profit includes Ivanhoe Mines' share of profit and finance income from the Kamoa-Kakula joint venture of $130 million for Q1 2023.
- Adjusted Q1 2023 EBITDA for the Ivanhoe Mines group of $168 million, compared to $145 million for the same period in 2022, and $162 million for Q4 2022, which includes an attributable share of EBITDA from Kamoa-Kakula.
- During Q1 2023, Kamoa-Kakula sold 86,777 tonnes of payable copper and recognized record revenue of $689 million, with an operating profit of $416 million and record quarterly EBITDA of $452 million.
- Kamoa-Kakula's cost of sales per pound (lb.) of payable copper sold was $1.25/lb. for Q1 2023 compared with $1.08/lb. and $1.08/lb. in Q4 2022 and Q1 2022, respectively. Cash costs (C1) per pound of payable copper produced in Q1 2023 totalled $1.42/lb., compared to $1.42/lb. and $1.21/lb. in Q4 2022 and Q1 2022, respectively.
- Ivanhoe Mines has a strong balance sheet with cash and cash equivalents of $497 million on hand as at March 31, 2023, and expects Kamoa-Kakula's Phase 1 and Phase 2 cash flow to be sufficient to fund the Phase 3 expansion capital cost requirements at current copper prices.
- Off-take and financing terms agreed with Gécamines and Glencore to return Ivanhoe's ultra-high-grade Kipushi Mine to production in Q3 2024; off-take term sheet for 100% of Kipushi's zinc concentrate, together with a $250-million facility to finance construction.
OPERATIONAL HIGHLIGHTS
- Kamoa-Kakula produced 93,603 tonnes of copper in Q1 2023, including a record 34,915 tonnes of copper in March 2023, following the completion of the debottlenecking program in late February 2023, ahead of schedule and on-budget.
- Kamoa-Kakula's Phase 1 and 2 concentrators have continued to perform strongly, achieving a daily mill throughput record of over 29,000 tonnes, and also achieving recoveries in excess of 88% during March and April, significantly higher than the design rate of 86%.
- Construction for Platreef's Phase 1 concentrator is advancing well and is on track for first production in Q3 2024. The Shaft 2 headgear concrete structure is complete to a height of approximately 79 metres. Shaft 2's overall height will be approximately 100 metres above ground, including the steel structure housing the main winders.
- Ivanhoe initiated an optimization study at Platreef to potentially accelerate production from the Phase 2 expansion. The study will consider the implications of converting the 5.1-metre-diameter ventilation shaft (Shaft 3), which is under construction, to a production shaft with the capability to hoist.
- Surface construction activities and underground development of the Big Zinc orebody at Kipushi are advancing ahead of schedule, with first concentrate production expected in Q3 2024.
- Ivanhoe continues its expansive copper exploration program on its Western Foreland licences that cover approximately 2,407 square kilometres adjacent to Kamoa-Kakula. Diamond drilling commenced in early January with a single contractor rig, which was increased to three rigs by the end of March, together with an Ivanhoe Land Cruiser mounted diamond drill rig. A total of 4,883 meters of diamond core was drilled during the quarter, which was wet season.
- Ivanhoe Mines published its sixth annual Sustainability Report, underscoring the company's ongoing commitment to "mining with a greater purpose" and its pursuit to be a global leader in responsible mining. Please visit www.ivanhoemines.com to view the report.
Watch a Q1 2023 video of operations and construction activities at Kamoa-Kakula: https://vimeo.com/823071306/8b676323fb
Read Ivanhoe's First Quarter 2023 Sustainability Update: https://bit.ly/40XMxeC
Q1 2023 conference call for investors
Ivanhoe Mines will hold an investor conference call to discuss its Q1 2023 financial results at 10:30 a.m. Eastern time / 7:30 a.m. Pacific time on Wednesday, May 3. The conference call will conclude with a question-and-answer (Q&A) session. Media are invited to attend on a listen-only basis.
To view the webcast please use the following link: https://edge.media-server.com/mmc/p/i6yyz97g
Analysts are invited to join by phone for the Q&A using the following link: https://register.vevent.com/register/BI639b8647ae7c4cf6802991597dd26b68
An audio webcast recording of the conference call, together with supporting presentation slides, will be available on Ivanhoe Mines' website at www.ivanhoemines.com.
After issuance, the Financial Statements and Management's Discussion and Analysis will be available at www.ivanhoemines.com and www.sedar.com.
Principal projects and review of activities
- Kamoa-Kakula Copper Complex
39.6%-owned by Ivanhoe Mines
Democratic Republic of Congo
The Kamoa-Kakula Copper Complex operated as the Kamoa Holding joint venture between Ivanhoe Mines and Zijin Mining, has been independently ranked as the world's third-largest copper deposit by international mining consultant Wood Mackenzie in 2027. The project is approximately 25 kilometres southwest of the town of Kolwezi and about 270 kilometres west of Lubumbashi. Kamoa-Kakula Copper Complex's Phase 1 concentrator began producing copper in May 2021 and achieved commercial production on July 1, 2021. The Phase 2 concentrator, which doubled nameplate production capacity, was commissioned in April 2022.
Ivanhoe sold a 49.5% share interest in Kamoa Holding Limited (Kamoa Holding) to Zijin Mining and a 1% share interest in Kamoa Holding to privately owned Crystal River in December 2015. Kamoa Holding holds an 80% interest in the project. Ivanhoe and Zijin Mining each hold an indirect 39.6% interest in Kamoa-Kakula, Crystal River holds an indirect 0.8% interest, and the DRC government holds a direct 20% interest. Kamoa-Kakula's employee workforce is currently 97% Congolese.


Kamoa-Kakula produced 93,603 tonnes of copper in Q1 2023, including a record 34,915 tonnes of copper in March 2023
Kamoa-Kakula's Phase 1 and 2 concentrators are now regularly operating at the increased processing rate of 9.2 million tonnes per annum (Mtpa), following the completion of the debottlenecking program. The $50-million Phase 1 and 2 concentrator debottlenecking program was completed on budget and ahead of schedule in late February 2023, increasing production capacity up to 450,000 tonnes of copper in concentrate per annum. All figures are on a 100% project basis and metal reported in concentrate is before refining losses or deductions associated with smelter terms.
Following the completion of the debottlenecking program in February, Kamoa-Kakula's Phase 1 and 2 concentrators had a record-breaking month in March for copper production, including a monthly production record of 34,915 tonnes of copper in concentrate, in addition to a weekly production record of 9,016 tonnes in mid-March, and a daily production record of 1,563 tonnes on March 25, 2023. These records were achieved following two scheduled plant shutdowns during the first quarter to tie in the new debottlenecking equipment. During the month of April, strong concentrator performance continued with a record daily mill throughput achieved of 29,206 tonnes of ore.
Kamoa-Kakula's Phase 1 and 2 concentrators milled approximately 1.93 million tonnes of ore during the first quarter at an average feed grade of 5.42% copper. This included approximately 255,000 tonnes of ore from the surface stockpiles.

The Phase 1 and Phase 2 concentrators also substantially outperformed design specifications in terms of copper recovery during the months of March and April. Copper recoveries averaged 88% and periodically exceeded 90% over a 24-hour periods. These record recoveries are significantly above Kamoa-Kakula's nameplate 86% recovery rate.
The record monthly production in March was also achieved despite previously reported instability within the southern DRC grid.
In response to the instability in the southern DRC grid experienced since December 2022, Kamoa-Kakula, together with DRC state-owned power company SNEL, completed a study to tackle the vulnerabilities exposed in the grid network.
Grid stability improved during the month of April, following some initial infrastructure management and maintenance initiatives that SNEL introduced with support from Kamoa Copper. In addition, 60 MW of additional generation capacity from the recently refurbished Nseke hydroelectric power station was introduced into the DRC network. Further initiatives will continue to be implemented over the coming year, benefiting not only the Kamoa-Kakula Copper Complex, but all users of the DRC's southern grid.
Kamoa-Kakula is also planning to protect operations from potential future grid instability with significantly increased on-site power generation capacity. The current installed backup generation capacity on-site is approximately 32 MW. Over time there is a plan to increase this to over 200 MW in a phased roll-out to achieve sufficient redundancy to meet the total power requirement for Phases 1, 2 and 3, excluding the smelter in situations where extended supply interruptions may occur.

In the roll-out plan, an additional 11 MW is expected to be commissioned in Q2 2023 with a further 49 MW planned to be delivered to site towards the end of 2023. Study work is underway on further options for additional on-site backup power capacity, including renewable options, such as solar and hydro, together with battery storage.
Discussions are well advanced to secure up to an additional 100 MW of power from Copperbelt Energy Corporation (CEC) of Zambia, via the DRC-Zambia interconnector. An agreement is expected to be in place shortly.
Draw-down of surface ore stockpiles at Kakula continues as required; stockpiles hold approximately 4.2 million tonnes grading 3.9% copper, containing more than 161,000 tonnes of copper
Kamoa-Kakula's high- and medium-grade ore surface stockpiles totaled approximately 4.2 million tonnes at an estimated grade of 3.9% copper as of the end of March 2023. Excluding any stockpile material, during Q1 2023 the operation mined 2.02 million tonnes of ore from the Kakula and Kansoko mines, grading 5.2% copper. This comprised of 1.83 million tonnes of ore grading 5.6% copper from the Kakula Mine, including 0.75 million tonnes grading 6.7% copper from the mine's high-grade centre.
While the ongoing expansion of underground infrastructure at the Kakula mine takes place, ore will be drawn as required from the stockpile to maximize copper production.
Civil construction for the Phase 3 concentrator plant and associated infrastructure is well advanced
Kamoa-Kakula's ongoing Phase 3 expansion is expected to be commissioned in Q4 2024 and includes a new 5.0-million-tonne-per-annum (Mtpa) concentrator at Kamoa, which is approximately 10 kilometres north of the Phase 1 and 2 concentrators.
The process design of the Phase 3 concentrator is very similar to that of the Phase 1 and 2 concentrators, only larger. The front end of the concentrator (stockpile, crushing and screening) is being built to a capacity of 10 Mtpa, double the required capacity for Phase 3, in anticipation of the future Phase 4 expansion. This follows the same construction approach as that of Phase 1 and Phase 2. The bulk of the equipment is the same or similar to that installed in the Phase 1 and 2 concentrators, resulting in a commonality of spare parts, while leveraging prior operational and maintenance experience.
Detailed design is nearing completion and procurement activities are advancing on schedule with all major equipment ordered and the first steel erection expected around June 2023. Earthworks are essentially complete and civil construction is well-advanced. The structural steel, piping and plate work (SMPP) construction contract is expected to be rewarded shortly.
------
For complete report: https://ivanhoemines.com/news/2023/ivanhoe-mines-issues-2023-first-quarter-financial-results-and-overview-of-construction-and-exploration-activities/
------
Disclosure of technical information
Disclosures of a scientific or technical nature in this news release regarding the Kamoa-Kakula Copper Complex (other than stockpiles estimation), the Platreef Project and the Kipushi Project have been reviewed and approved by Steve Amos, who is considered, by virtue of his education, experience and professional association, a Qualified Person under the terms of NI 43-101. Mr. Amos is not considered independent under NI 43-101 as he is the Executive Vice President, Projects, at Ivanhoe Mines. Mr. Amos has verified the technical data related to the foregoing disclosed in this news release.
Disclosures of a scientific or technical nature regarding the Kamoa-Kakula stockpiles in this news release have been reviewed and approved by George Gilchrist, who is considered, by virtue of his education, experience and professional association, a Qualified Person under the terms of NI 43-101. Mr. Gilchrist is not considered independent under NI 43- 101 as he is the Vice President, Resources, at Ivanhoe Mines. Mr. Gilchrist has verified the technical data regarding the Kamoa-Kakula stockpiles disclosed in this news release.
Disclosures of a scientific or technical nature regarding the Western Foreland Project in this news release have been reviewed and approved by Stephen Torr, who is considered, by virtue of his education, experience and professional association, a Qualified Person under the terms of NI 43-101. Mr. Torr is not considered independent under NI 43-101 as he is the Vice President, Geosciences, at Ivanhoe Mines. Mr. Torr has verified the technical data regarding the Western Foreland Project disclosed in this news release.
Ivanhoe has prepared an independent, NI 43-101-compliant technical report for the Kamoa-Kakula Project, the Platreef Project and the Kipushi Project, each of which is available on the company's website and under the company's SEDAR profile at www.sedar.com:
- Kamoa-Kakula 2023 IDP Technical Report dated March 6, 2023, prepared by OreWin Pty Ltd.; China Nerin Engineering Co. Ltd.; DRA Global; Epoch Resources; Golder Associates Africa; Metso Outotec Oyj; Paterson and Cooke; SRK Consulting Ltd.; and, The MSA Group.
- The Kipushi 2022 Feasibility Study dated February 14, 2022, prepared by OreWin Pty Ltd., MSA Group (Pty) Ltd., SRK Consulting (South Africa) (Pty) Ltd, and METC Engineering.
- The Platreef 2022 Feasibility Study dated February 28, 2022, prepared by OreWin Pty Ltd., Mine Technical Services, SRK Consulting Inc., DRA Projects (Pty) Ltd and Golder Associates Africa.
These technical reports include relevant information regarding the effective dates and the assumptions, parameters and methods of the mineral resource estimates on the Platreef Project, the Kipushi Project and the Kamoa-Kakula Copper Complex cited in this news release, as well as information regarding data verification, exploration procedures and other matters relevant to the scientific and technical disclosure contained in this news release in respect of the Platreef Project, Kipushi Project and Kamoa-Kakula Copper Complex.
The Kamoa-Kakula 2023 PFS and Kamoa-Kakula 2023 PEA were independently prepared by OreWin Pty Ltd. of Adelaide, Australia; China Nerin Engineering Co., Ltd., of Jiangxi, China; DRA Global of Johannesburg, South Africa; Epoch Resources of Johannesburg, South Africa; Golder Associates Africa of Midrand, South Africa; Metso-Outotec Oyj of Helsinki, Finland; Paterson and Cooke of Cape Town, South Africa; SRK Consulting Inc. of Johannesburg, South Africa; and MSA Group of Johannesburg, South Africa.
For the recently announced Kamoa-Kakula 2023 IDP (including the Kamoa-Kakula 2023 PFS and Kamoa-Kakula 2023 PEA), a new, independent NI 43-101 technical report was filed on SEDAR at www.sedar.com and the Ivanhoe Mines website at www.ivanhoemines.com on March 16, 2023.
Information contact
Follow Robert Friedland (@robert_ivanhoe) and Ivanhoe Mines (@IvanhoeMines_) on Twitter.
Investors
Vancouver: Matthew Keevil +1.604.558.1034
London: Tommy Horton +44 7866 913 207
Media
Tanya Todd +1.604.331.9834
Website www.ivanhoemines.com
Forward-looking statements
Certain statements in this news release constitute "forward-looking statements" or "forward-looking information" within the meaning of applicable securities laws. Such statements and information involve known and unknown risks, uncertainties and other factors that may cause the actual results, performance or achievements of the company, its projects, or industry results, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information. Such statements can be identified using words such as "may", "would", "could", "will", "intend", "expect", "believe", "plan", "anticipate", "estimate", "scheduled", "forecast", "predict" and other similar terminology, or state that certain actions, events, or results "may", "could", "would", "might" or "will" be taken, occur or be achieved. These statements reflect the company's current expectations regarding future events, performance and results and speak only as of the date of this news release.
Such statements include without limitation, the timing and results of: (i) statements regarding Kamoa-Kakula's Phase 3 expansion targeted for Q4 2024 completion, which is expected to increase copper production to a ten-year average of 620,000 tonnes per annum, at C1 cash cost of $1.22/lb, which expansion includes a new 5.0 Mtpa concentrator; (ii) statements regarding the ultra-high-grade Kipushi zinc-copper-germanium-silver mine being on track for first production in Q3 2024, and project financing being near completion; (iii) statements regarding the Platreef palladium, nickel, platinum, rhodium, copper and gold project in South Africa being scheduled for first production in Q3 2024; (iv) statements that the Kamoa 1 and Kamoa 2 mines will become the main providers of copper ore for Kamoa-Kakula's Phase 3 expansion to over 600,000 tonnes of copper production annually by Q4 2024; (v) statements regarding the installation of a state-of-the-art static compensation unit at the Kolwezi converter station to stabilize the entire southern grid network and provide a significantly improved electricity supply to Kamoa-Kakula; (vi) statements regarding the over-time increase of backup generation capacity on-site at Kamoa Kakula to over 200 MW in a phased roll-out to achieve sufficient redundancy to meet the total power requirement of the mine in situations where extended supply interruptions may occur, with additional 11 MW expected in Q2 2023 and a further 49 MW expected delivered to site toward the end of 2023, all of which is expected to be sufficient power for Phases 1, 2 and 3, excluding the smelter; (vii) statements regarding an agreement to secure up to an additional 100 MW of power from CEC of Zambia, via the DRC-Zambia interconnector, for Kamoa Kakula; (viii) statements that while the ongoing expansion of underground infrastructure at the Kakula mine takes place, ore will be drawn as required from the stockpile to maximize copper production; (ix) statements that commissioning of Phase 3 at Kamoa-Kakula will result in total processing capacity of over 14.2 Mtpa and that this will position Kamoa Copper as the world's third largest copper mining complex and the largest copper mine on the African continent; (x) statements regarding the 2023 exploration program at Western Foreland being approximately $19 million and including up to 70,000 meters of total drilling; (xi) statements regarding the planned release of a maiden Mineral Resource estimate for its Makoko and Kiala high-grade copper discoveries in the Western Foreland in mid-2023; (xii) statements regarding the optimization study at its Tier-One Platreef palladium, nickel, platinum, rhodium, copper and gold mine in South Africa potentially accelerating production from the Phase 2 expansion, which has the benefit of de-risking the development and ramp-up of the Phase 1 mine and may be used to accelerate the ramp-up of underground mining activities for Phase 2, in advance of the completion of Shaft 2, which is expected in 2027; (xiii) statements that the Lualaba Copper Smelter will produce between 650,000 and 800,000 tonnes per annum of high-strength sulphuric acid that is expected to be sold in the domestic DRC market; (xiv) statements that the on-site smelter will offer transformative financial benefits for the Kamoa-Kakula Copper Complex, most notably of which is a material reduction in logistics costs (which volume of shipments per unit of copper are expected to be more than halved by selling 99+%-pure blister copper anodes instead of copper concentrate), and to a lesser extent reduced concentrate treatment charges and local taxes, as well as revenue from the acid sales; (xv) statements regarding smelter commissioning being expected to drive a decrease in average cash costs (C1) over the first five years (from 2025) to approximately $1.15/lb. of copper, a 21% reduction from the midpoint of the 2023 guidance of $1.45/lb. of payable copper produced; (xvi) statements regarding the Phase 3 concentrator at Kamoa-Kakula being on track for first concentrate in Q4 2024 (which is planned to coincide with the commissioning of an on-site, direct-to-blister flash copper smelter capable of producing 500,000 tonnes per annum of copper anode), and that it will be fed with ore from the existing Kansoko Sud Mine (formerly Kansoko Mine), as well as new mines currently under development in the Kamoa area, known as Kamoa 1 and 2; (xvii) statements regarding the Phase 4 expansion of the Kamoa-Kakula concentrator taking total processing capacity up to 19.2 Mtpa, and that the Phase 4 concentrator will be fed by new mines in the Kamoa area; (xix) statements that the turbine replacement will supply an additional 178-megawatts of clean hydroelectric power to the national grid, and provide power for Phase 3; (xx) statements regarding the first steel erection with respect to the Kamoa Phase 3 concentrator being expected in June 2023;(xxi) statements regarding the Kamoa-Kakula Phase 3 expansion incorporating leading-edge technology supplied by Metso Outotec, which smelter is projected to be one of the largest, single-line copper flash smelters in the world, with a production capacity of 500,000 tonnes per annum of blister copper anodes; (xxii) statements regarding the Kamoa-Kakula Phase 3 smelter having a processing capacity of 1.2Mtpa of dry concentrate feed and being designed to run a blend of concentrate produced from the Kakula (Phase 1 and 2) and Kamoa (Phase 3 and Phase 4) concentrators; (xxiii) statements that Kamoa-Kakula will continue to toll-treat concentrates under a 10-year agreement with the Lualaba Copper Smelter, which is expected to account for approximately 150,000 tonnes of copper concentrate annually, with the balance of copper production being exported as concentrate; (xxiv) statements that construction of the twin declines to the Kamoa 1 and Kamoa 2 underground mines and excavation access to Phase 3 mining areas are advancing well; (xxv) statements that underground mining activities at Kamoa 1 are expected to commence in 2023 and at Kamoa 2 in 2025, and which both involved the same mechanized drift-and-fill mining methods employed at the Kakula mine; (xxvi) statements regarding the future expansions of the Kamoa-Kakula Copper Complex being powered by clean, renewable hydro-generated electricity which will be developed in partnership with the DRC's state-owned power company SNEL; (xxvii) statements that the refurbishment of the Inga II hydropower facility on the Congo River is on schedule; (xxviii) statements that the Phase 1 and 2 concentrators will continue to process ore from the Kakula Mine, as well as the new adjacent Kakula West Mine from 2029; (xxix) statements regarding Kamoa-Kakula 2023 guidance including contained copper in concentrate of 390,000 to 430,000 tonnes and cash cost (C1) of $1.40 to $1.50 per lb; (xxx) statements that a senior debt facility for Platreef is targeted for completion in the first half of 2023; (xxxi) statements that Shaft 3 at Platreef is scheduled to be completed in Q4 2023; (xxxii) statements that first production at Platreef's Phase 1 concentrator is scheduled for Q3 2024, with majority long-lead equipment orders scheduled for delivery in Q3 2023; (xxxiii) statements that an additional senior credit facility for Platreef is targeted for completion in mid-2023; (xxxiv) statements that the EC&I contract award at Platreef is planned for mid-2023 with site mobilization expected in Q3 2023; (xxxv) statements that the 10-metre diameter Shaft 2 currently under construction will have a hoisting capacity of 8 Mtpa and that Shaft 2 will be utilized in subsequent development phases and will be among the largest hoisting shafts in the world; (xxxvi) statements that the commissioning of Platreef's first solar-power plant is expected in 2023 and that the solar-generated power from the plant will be used for mine development and construction activities, and that the power generated by this plant will support development activities and operations, together with other renewable energy sources to be introduced over time; (xxxvii statements regarding the pilot drilling required for the raise bore center hole of Platreef's Shaft 2 being scheduled to finish during Q2 2023, after which reaming of a 3.1-meter diameter hole is planned; (xxxviii) statements regarding the raise-boring of the 5.1-meter diameter ventilation shaft (Shaft 3) expected to be completed in Q4 2023; (xxxix) statements that equipping Shaft 3 at Platreef with hoisting capacity will provide alternative option to remove ore and waste from the underground mine, which may accelerate ramp-up of underground mining activities for Phase 2; (xl) statements that underground mining activities for Phase 2 at Platreef are expected in 2027; (xli) statements regarding the off-take term sheet, and the entering into definitive agreements with respect thereof, between Kipushi Corporation SA and Gécamines, and the terms of a $250 million term financing facility for Kipushi from Glencore; (xlii) statements regarding the signed agreement between Kipushi Holding and Gécamines to return the ultra-high-grade Kipushi Mine to commercial production, which sets out the commercial terms that will form the basis of a new Kipushi joint-venture agreement establishing a robust framework for the mutually beneficial operation of Kipushi for years to come, which are subject to execution of definitive documentation; (xliii) statements regarding the impact of the joint venture agreement with Gécamines on Ivanhoe Mines' ownership in the Kipushi Project, which is expected to be reduced to 62%, with Gécamines holding the balance of 38%, and the highlights of the new agreement;(xliv) statements that long lead order equipment packages for Kipushi are expected to commence delivery to the site in late summer 2023, with the ball mill delivery planned for Q3 2023; (xlv) statements that first concentrate at Kipushi is on schedule to occur during Q3 2024; (xlvi) statements that Shaft 5 at Kipushi is planned to be the main production shaft with a maximum hoisting capacity of 1.8Mtpa; (xlvii) statements that mining at Kipushi will be performed using highly productive, mechanized methods and that cemented rock fill will be utilized to backfill open stopes with tailings from the surface to reduce surface tailings and maximize ore extraction at Kipushi, where ore is expected to be crushed underground and conveyed to the base of the P5 shaft where it will be hoisted to the surface and conveyed to the nearby run-of-mine stockpile, adjacent to the 800,000-tonne-per-annum concentrator; (xlviii) statements that stoping at the Big Zinc orebody is expected to commence in early 2024 to build a high-grade ore stockpile ahead of processing plant commissioning in Q3 2024; (xlix) statements that gravity survey at the Mokopane Feeder Exploration Project will commence in Q2 2023, and that diamond drilling will be conducted later in the year on targets to be identified from the results of the magnetic and gravity surveys; (l) statements that a new commercial border crossing between DRC-Zambia will provide significant advantage to Kipushi Mine as a direct means of importing materials and consumables and clearing customs, and that it will provide socio-economic benefits to the town and Province of Haut-Katanga; (li) statements that a new commercial border crossing between DRC-Zambia will benefit logistics for Kamoa-Kakula's operations; (lii) statements that diamond drilling is expected to be conducted on the Mokopane Feeder Exploration Project in 2023; (liii) statements that Phase 1 and Phase 2 operations at Kamoa-Kakula are anticipated to generate significant operating cash flows in 2023 and 2024, and are expected to fund capital cost requirements at current copper prices, and that the joint venture is arranging short-term financing facilities should a shortfall occur due to a significant decrease in copper prices; (liv) statements with respect to the Company's planned expenditures for 2023 and 2024; and (lv) statements that 2023 exploration activities have an initial budget of $31 million.
As well, all of the results of the feasibility study for the Kakula copper mine, the Kamoa-Kakula 2023 IDP, the Platreef 2022 feasibility study, and the Kipushi 2022 feasibility study constitute forward-looking statements or information and include future estimates of internal rates of return, net present value, future production, estimates of cash cost, proposed mining plans and methods, mine life estimates, cash flow forecasts, metal recoveries, estimates of capital and operating costs and the size and timing of phased development of the projects.
Furthermore, concerning this specific forward-looking information concerning the operation and development of the Kamoa-Kakula Copper Complex, Platreef and Kipushi projects, the company has based its assumptions and analysis on certain factors that are inherently uncertain. Uncertainties include: (i) the adequacy of infrastructure; (ii) geological characteristics; (iii) metallurgical characteristics of the mineralization; (iv) the ability to develop adequate processing capacity; (v) the price of copper, nickel, zinc, platinum, palladium, rhodium and gold; (vi) the availability of equipment and facilities necessary to complete development; (vii) the cost of consumables and mining and processing equipment; (viii) unforeseen technological and engineering problems; (ix) accidents or acts of sabotage or terrorism; (x) currency fluctuations; (xi) changes in regulations; (xii) the compliance by joint venture partners with terms of agreements; (xiii) the availability and productivity of skilled labour; (xiv) the regulation of the mining industry by various governmental agencies; (xv) the ability to raise sufficient capital to develop such projects; (xvi) changes in project scope or design; (xvii) recoveries, mining rates and grade; (xviii) political factors; (xviii) water inflow into the mine and its potential effect on mining operations, and (xix) the consistency and availability of electric power.
This news release also contains references to estimates of Mineral Resources and Mineral Reserves. The estimation of Mineral Resources is inherently uncertain and involves subjective judgments about many relevant factors. Estimates of Mineral Reserves provide more certainty but still involve similar subjective judgments. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. The accuracy of any such estimates is a function of the quantity and quality of available data and of the assumptions made and judgments used in engineering and geological interpretation (including estimated future production from the company's projects, the anticipated tonnages and grades that will be mined and the estimated level of recovery that will be realized), which may prove to be unreliable and depend, to a certain extent, upon the analysis of drilling results and statistical inferences that ultimately may prove to be inaccurate. Mineral Resource or Mineral Reserve estimates may have to be re-estimated based on: (i) fluctuations in copper, nickel, zinc, platinum group elements (PGE), gold or other mineral prices; (ii) results of drilling; (iii) metallurgical testing and other studies; (iv) proposed mining operations, including dilution; (v) the evaluation of mine plans after the date of any estimates and/or changes in mine plans; (vi) the possible failure to receive required permits, approvals and licences; and (vii) changes in law or regulation.
Forward-looking statements and information involve significant risks and uncertainties, should not be read as guarantees of future performance or results and will not necessarily be accurate indicators of whether such results will be achieved. Many factors could cause actual results to differ materially from the results discussed in the forward-looking statements or information, including, but not limited to, the factors discussed above and under the "Risk Factors" section in the company's MD&A for the three months ended March 31, 2023, and its Annual Information Form, and elsewhere in this news release, as well as unexpected changes in laws, rules or regulations, or their enforcement by applicable authorities; the failure of parties to contracts with the company to perform as agreed; social or labour unrest; changes in commodity prices; and the failure of exploration programs or studies to deliver anticipated results or results that would justify and support continued exploration, studies, development or operations.
Although the forward-looking statements contained in this news release are based upon what management of the company believes are reasonable assumptions, the company cannot assure investors that actual results will be consistent with these forward-looking statements. These forward-looking statements are made as of the date of this news release and are expressly qualified in their entirety by this cautionary statement. Subject to applicable securities laws, the company does not assume any obligation to update or revise the forward-looking statements contained herein to reflect events or circumstances occurring after the date of this news release.
The company's actual results could differ materially from those anticipated in these forward-looking statements as a result of the factors outlined in the "Risk Factors" section and elsewhere in the company's MD&A for the three months ended March 31, 2023, and its Annual Information Form.
More Info:
Disclaimer/Disclosure: Investorideas.com is a digital publisher of third party sourced news, articles and equity research as well as creates original content, including video, interviews and articles. Original content created by investorideas is protected by copyright laws other than syndication rights. Our site does not make recommendations for purchases or sale of stocks, services or products. Nothing on our sites should be construed as an offer or solicitation to buy or sell products or securities. All investing involves risk and possible losses. This site is currently compensated for news publication and distribution, social media and marketing, content creation and more. Disclosure is posted for each compensated news release, content published /created if required but otherwise the news was not compensated for and was published for the sole interest of our readers and followers. Contact management and IR of each company directly regarding specific questions.
More disclaimer info: https://www.investorideas.com/About/Disclaimer.asp Learn more about publishing your news release and our other news services on the Investorideas.com newswire https://www.investorideas.com/News-Upload/
Global investors must adhere to regulations of each country. Please read Investorideas.com privacy policy: https://www.investorideas.com/About/Private_Policy.asp